Flagler 100

Project Details

Project Size: 112,500
Project Cost: $510,288.00

Roof System

5” of isocyanurate rigid roof insulation (R-28.8), mechanically fastened directly over the existing modified bitumen roof system.
Carlisle 115 mil fleece back TPO membrane mechanically attached.

Project Challenges

Prior to the new roof installation, 20 large HVAC units had to be disconnected and removed by crane, the holes in the deck covered with new steel decking and the existing roof patched with modified bitumen membrane.

Warranty

The project included a 20-year Manufacturer’s warranty covering materials and labor, as well as 2-year Contractor’s workmanship warranty from McCurdy-Walden.